With rain forecasted throughout the day, we decided to pause work. With that said, we do have plans to visit the tile shop. The backsplash tiles have yet to be selected, let alone ordered.
Some key things that happened today:
Shopping for Tiles
We ventured to The Tile Shop to peruse their selections on display. We’re thinking of doing a herringbone or picket pattern. Preferably a very light gray tone. I took a few shots of interesting options, but we didn’t find anything that immediately popped out as THE ONE. We’ll be looking at a few more places. Thankfully we have some time.
Start Packing
Armin told us he thinks we may want to move out as early as next Fri, so we started packing away kitchen stuff into boxes to store away in the basement.
Bar Sink Arrives
The bar sink arrived today. With that we just need the bar faucet, glass rinser, and garbage disposal, which are all ordered and on the way.